It is valuation time again for my office (09/30) annual plans. Only the second year on Quantech some we have some pretty basic questions.... I have a date of hire of 03/03/98 - date of entry is first day following one year of service which should be 04/01/99, but the system is calculating 03/01/99. I made sure that the "credit full month for any service" is NOT checked. The system calculated correctly on all but one person on two plans? Any suggestions?

Posted

You might give Quantech a call and see if you can export the plan to them for review.

Posted

what do you have answered for "Waiting period exclusive"

example: ee hired 3/2

if not checked, ee completes 1 year on 3/1, if monthly entry, would enter 3/1.

if checked, ee completes 1 year on 3/2 and wouldn't enter until 4/1.

granted, if ee was hired 3/3 system should make him wait until 4/1, but because plan is not calendar year, maybe system is having a brain freeze. I agree, you may have to ask them directly if all things are coded as you indicated. still, you might want to try 'exclusive' logic.

by the way,

since you indicated you were a fairly new user, one item you might want to change in plan specs (this has no effect on your question, but is a suggestion) is

'past years service computation'.

once a plan has been processed one year, this item should probably be set to 'not computed' if you have it set to 'half years credited'

Posted

Thank you - the problem was the waiting period exclusive. Works beautifully now.

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...

Important Information

Terms of Use