cpc0506 Posted August 29, 2016 Posted August 29, 2016 Participant A took a hardship and Employer did not stop deferrals as required. I know that the deferrals need to be returned to the participant, but are the deferrals included in the ADP Test?
Lou S. Posted August 29, 2016 Posted August 29, 2016 HCE or NHCE? I think the answer is different depending. If it was an HCE you include the, If it is an NHCE you exclude them.
Tom Poje Posted August 29, 2016 Posted August 29, 2016 my guess would have been they are not counted at all. they are a 'mistake' - if you are self correcting you are putting a plan in a position as if the error hadn't occurred. this is different than if there are excess deferrals in which the regs clearly spell out what is to be done.