Guest furiousfurrball Posted April 30, 2008 Posted April 30, 2008 If a plan performed it's 2006 NDT testing and failed the ADP test but due to a variety of reasons during 2007 it did not refund the excess contributions to HCEs, can they do it in 2008? Is there a way to correct this and make it right?
BG5150 Posted May 1, 2008 Posted May 1, 2008 Consider EPCRS, Rev. Proc. 2006-27 Attached here for your consideration EPCRS.pdf QKA, QPA, CPC, ERPATwo wrongs don't make a right, but three rights make a left.